Chelsea & Westminster Hospital

Project Location:
Fulham Road, London


Client / End User:
Interspace Ltd / NHS Trust


Contract Value:
£1,000,000


Contract Duration:
29 weeks


Electrical installation for alterations and refurbishment to a diagnostic and treatment centre including new and existing day theatres, recovery and treatment areas and associated nursing facilities.

This was a complex project to undertake as the hospital needed to be kept fully occupied and operational throughout the duration of the work. Works were phased to maintain existing systems, whilst the existing installation was surveyed, isolated, supplied from alternative locations, removed, reinstated and then brought on line.

Installation works included general and emergency lighting and power, an isolated power supply system for theatres, a fire alarm system, CCTV, access control , voice and data containment and a nurse call system.